How many business days prior to TD-1 must the Activity and Training Environmental Management Plans (ATEMP) Form EMP 13.1.1 be delivered to Range Control?

Prepare for the Camp Butler OIC/RSO Test with flashcards and multiple choice questions. Each question comes with hints and explanations. Get ready to ace your exam!

The correct answer is 10 business days. This timeframe is established to ensure that Range Control has adequate notice to review and process the Activity and Training Environmental Management Plans (ATEMP) Form EMP 13.1.1. By requiring submission 10 business days prior to TD-1, it allows for the necessary checks, approvals, and coordination that must occur before activities can commence. This also helps in managing resources effectively and ensuring compliance with environmental regulations. Ensuring timely submission is crucial for operational planning and safeguarding environmental standards during training activities.